|
|
Saturdays 8-10am | 92.1 FM WKUL
The construction project – from beginning, middle to end
By Larry Logsdon

Whether from the prospective of an
owner, general contractor or subcontractor,
engaging in any new construction
project brings emotions of both excited
anticipation and fear of the unknown.
Having a precise and complete plan as to
how the project will be handled at each
phase will help to make it more successful
and enjoyable.
Having an early snapshot of potential
issues that could arise can bring to
the forefront the expectations of all parties
involved and work to alleviate future
disagreements as the project progresses.
The construction contract documents
the expectations of the parties prior to
work beginning and is essential for any
construction job. It is like insurance in
many ways as it provides help, guidance
and assurance when disputes do arise.
After agreeing on the price, the first
issues to consider in the contract relate
to the time of completion of the project.
In addition to the completion date, the
parties should address how delays that
inevitably arise will be handled.
Both the contractor and the owner want
an early completion time. The owner
wants to get the project finished so that
the building or structure can start earning
revenue or serve its intended purpose.
The contractor wants to earn its compensation
as quickly as possible and move on
to other jobs.
Delays cost money to both sides. Things
such as bad weather, changes in the work,
labor strikes, changes in the plans and
unforeseen conditions can all cause
delays. The parties should set out in the
contract what changes will allow for an
extension of completion time and whether
the delay will provide for additional
compensation to the contractor.
Along this line, another issue is whether,
and to what extent, the contract will allow
for liquidated damages to be imposed if
the work is not finished on time.
Next, a contract typically also will
address how often payments are to be
made, when payment must be made
in relation to when it is requested, how
much retainage should be withheld and
when retainage should be released.
The contract likely also will address
what conditions must be satisfied before
payment is made. These conditions can
include things such as the approval of the
work by an architect or the submission of
lien releases.
Also, in a contract between a contractor
and subcontractor is a “pay when paid”
or “pay if paid” provision that makes payment
to the subcontractor by the contractor
conditional upon payment by the
owner to the contractor.
The parties also should consider how
they will handle conditions that occur on
the project that are different from what
might have been expected.
Typically, this involves conditions that
are either not what was apparent from the
plans and specifications or not what was
indicated by a visual review of the site.
This could include things such as hidden
rocks or unexpected soil conditions.
Other miscellaneous provisions of the
contract are: the types of warranties that
will be provided by the contractor and the
limitations to those; the conditions that
allow for, and the ramifications of, terminating
the contract; the required types
and amounts of insurance and bonding;
and whether disputes will be handled in
arbitration or in court.
Documentation of the project
As the project begins it is critical that all
parties have detailed documentation of
what takes place on the job. Many times
disputes over construction do not reach
trial or arbitration until long after the
events about which the parties disagree
have passed. Because of that, both the
contractor and owner should have a daily
diary of the project to support their side.
This documentation should include
things such as daily weather conditions; a
narrative and pictures showing site conditions;
who was (and was not) on the job
and when they were there; what supplies
or materials were on the project; the stage
of the project; a summary of discussions
and agreements that took place; problems
that occurred; and a description of
change orders and change directives.
In cases where the work is delayed or
potentially delayed the parties should
keep up with all events surrounding the
delay and all costs attributable to those
events.
Correspondence between the parties
also is necessary and in cases required
under notice and other provisions of the
contract.
Change orders and change directives
should be in writing and signed by both
parties.
Written notice should be given of any
events that can cause delay or potentially
allow for additional compensation.
Correspondence should be sent confirming
important conversations. Notification
should be given of defective work.
Finally, correspondence should be sent
in response to correspondence that is
received but disputed. Perhaps nowhere
is this more important than when disputed
pay requests are received, as many
states have “prompt payment” statutes
and these can include provisions for disputing
the request for payment in writing
within a certain number of days when
they are received.
As the project comes to a close, if problems
are to arise it is not uncommon for
them to be centered around either nonpayment
by the owner or the discovery of
a contractor’s defective work.
Non-payment options
As to non-payment, the contractor has
several tools that can be utilized to obtain
amounts that are owed. First, Alabama
and many other states, have adopted
prompt payment acts that set out
requirements for paying amounts that
are due. These statutes, when applicable,
can have provisions for when payment
must be made and allow for the recovery
of attorneys’ fees and interest in instances
of non-payment.
Next, a lien can be filed and if ultimately
perfected can allow the lien holder to
have a type of security in the property to
the extent of the amount they are owed. It
should be noted that the proper perfection
of a lien may require that the party
claiming the lien comply with various
specific notices prior to the filing of the
lien.
Also, lien statutes impose strict and
rigid deadlines on the timing of the lien
filing and the initiation of the lawsuit to
perfect the lien. The lien statutes also
contain precise form requirements on the
substance what must be contained in the
lien and the location of filing. Finally, in
instances where a job is bonded, a subcontractor
may have claims against not
only the contractor that owes money but
also against a bonding company.
From the owners perspective, the close
of the job may reveal problems with
work done by the contractor. The owner
should do all that they can to diagnose
and document the nature and extent of
the problem and notify the contractor of
its existence. Many contracts also contain
provisions requiring the owner to give
the contractor an opportunity to cure the
problem.
In connection with issues of non-payment
from the contractor’s perspective
or from the owner's standpoint, the contractor’s
failure to timely and properly
complete the work there may be considerations
of whether the contract should
be terminated. If a decision is made to
terminate, both the contractor and the
owner should carefully document all
events supporting that termination and
ensure that they are in compliance with
all notices and prerequisites to termination
set out in the contract.
What is listed above is only an attempt
to give a very general overview of what
should be considered in any construction
project.
Following all the needed steps may
seem tedious but knowing your rights
can pay tremendous dividends.
LARRY S. LOGSDONis a lawyer with
Wallace Jordan Ratliff & Brandt LLC in
Birmingham. He practices in general
commercial litigation and also represents
contractors, subcontractors, owners
and suppliers involved in all aspects
of the construction industry. He can be
reached at (205) 870-0555 or by e-mail
ll@wallacejordan.com.
|